Domestic Underfloor heating Project

Underfloor Heating Installation – Westmeath 2016

  • 17mm PE-RT pipe tacked to 150mm floor insulation
  • Heating pipe laid at 100mm centres for optimum heat pump efficiency
  • Doorway Expansion Joint Protection
  • UFH Manifolds in GF Utility and FF Walk in Wardrobe
  • System filled with 300L rain water to eliminate lime/contaminants
  • Customer then poured 60-70mm concrete screed floor over the UFH system
  • Geothermal Heat pump was then switched¬† to a 14 day Concrete Dry Out setting